Clifton Views Construction Update

It is not long now until the completion of this exciting project.  (See below for completion estimations)  This has been a long awaited project that we have all looked forward to.  We will continue to keep you informed of when construction is complete and the next step in the process for you.

Those in stage 1 will have talked to Wendy and will be aware that you need to be speaking with your broker/financier to organise your finances now.

Glencorp Property Management are very efficient when it comes to finding a tenant for your property and will begin the process as soon as the certificate of occupation has been issued.  This will be issued before the certificate of completion and will allow the property manager to begin advertising and set a date for the lease to begin.

We recently finished an updated Area Research Report on the Cairns region with the latest information on its industries, infrastructure, development and property market.  Click here if you would like to take a look at this.

Again, keep in touch with your property strategist and/or Wendy as you move towards settlement and don’t hesitate to call if you have any queries or concerns.

Stage 1

Building 25

  • Internal cleaning in progress
  • Carpet install in progress

Building 24

  • Internal painting complete

Building 23

  • Plasterer complete
  • Painters to start internal gloss work on Friday 14/11/2008

Stage 2

Building 22

  • Internal painting ready to start
  • Granite bench tops on site

Building 21

  • Building ready for defecting by supervisor
  • Plumbing, electrical and air conditioning fit offs complete

Building 20

  • Plumbing & electrical fit off 80% complete

Building 19

  • Building ready for defecting by supervisor
  • Plumbing, electrical & airconditioning fit offs complete

Building 18

  • Carpentry second fix (skirting, doors, door frames) 50%
  • Ceiling fan and air condition head unit install complete

Building 17

  • Kitchen install complete
  • Main floor tiles laid
  • Waterproofing complete in wet areas and ready for tiles

Building 16

  • Ground & first floor ready for painter to start
  • Second floor kitchens installed

Stage 3

Building 15

  • First floor block work complete
  • Scaffold raised and ready to start second floor formwork

Building 14

  • First floor block work 80% complete

Building 13

  • Second floor suspended slab reinforcement in progress
  • Second floor suspended slab pour booked for Monday 17/11/08

Stage 4

Building 12

  • Ground & first floor ready for painter to start

Building 11

  • Internal plasterboard wall linings 85%

Building 10

  • Internal plasterboard wall linings 40%

Building 9

  • Fire check ceilings to top floor completed

Building 8

  • Roof tiling 85%
  • Ground floor internal wall frames completed

Building 7

  • Ground & first floor internal wall framing completed

Building 6

  • External textured render 70%
  • Ground & first floor internal wall framing completed

Building 5

  • Ground floor slab formwork complete
  • Slab pour booked for Wednesday 19/11/08

Building 4

  • Ground pad completed

Estimated completion -

Stage One - 30/11/2008
Stage Two - Jan/Feb 2009

Related Posts

1 Star2 Stars3 Stars4 Stars5 Stars (No Ratings Yet)
Loading ... Loading ...

Tags: , , , , , , , , , , , , , , , , , , , , , , , , , , , , , ,

© 2008 mrd your property investmentmentor.com.au

Leave a Reply