Clifton Views Construction Update
It is not long now until the completion of this exciting project. (See below for completion estimations) This has been a long awaited project that we have all looked forward to. We will continue to keep you informed of when construction is complete and the next step in the process for you.
Those in stage 1 will have talked to Wendy and will be aware that you need to be speaking with your broker/financier to organise your finances now.
Glencorp Property Management are very efficient when it comes to finding a tenant for your property and will begin the process as soon as the certificate of occupation has been issued. This will be issued before the certificate of completion and will allow the property manager to begin advertising and set a date for the lease to begin.
We recently finished an updated Area Research Report on the Cairns region with the latest information on its industries, infrastructure, development and property market. Click here if you would like to take a look at this.
Again, keep in touch with your property strategist and/or Wendy as you move towards settlement and don’t hesitate to call if you have any queries or concerns.
Stage 1
Building 25
- Internal cleaning in progress
- Carpet install in progress
Building 24
- Internal painting complete
Building 23
- Plasterer complete
- Painters to start internal gloss work on Friday 14/11/2008
Stage 2
Building 22
- Internal painting ready to start
- Granite bench tops on site
Building 21
- Building ready for defecting by supervisor
- Plumbing, electrical and air conditioning fit offs complete
Building 20
- Plumbing & electrical fit off 80% complete
Building 19
- Building ready for defecting by supervisor
- Plumbing, electrical & airconditioning fit offs complete
Building 18
- Carpentry second fix (skirting, doors, door frames) 50%
- Ceiling fan and air condition head unit install complete
Building 17
- Kitchen install complete
- Main floor tiles laid
- Waterproofing complete in wet areas and ready for tiles
Building 16
- Ground & first floor ready for painter to start
- Second floor kitchens installed
Stage 3
Building 15
- First floor block work complete
- Scaffold raised and ready to start second floor formwork
Building 14
- First floor block work 80% complete
Building 13
- Second floor suspended slab reinforcement in progress
- Second floor suspended slab pour booked for Monday 17/11/08
Stage 4
Building 12
- Ground & first floor ready for painter to start
Building 11
- Internal plasterboard wall linings 85%
Building 10
- Internal plasterboard wall linings 40%
Building 9
- Fire check ceilings to top floor completed
Building 8
- Roof tiling 85%
- Ground floor internal wall frames completed
Building 7
- Ground & first floor internal wall framing completed
Building 6
- External textured render 70%
- Ground & first floor internal wall framing completed
Building 5
- Ground floor slab formwork complete
- Slab pour booked for Wednesday 19/11/08
Building 4
- Ground pad completed
Estimated completion -
Stage One - 30/11/2008
Stage Two - Jan/Feb 2009
Related Posts
Tags: 40%, air conditioning, amp, broker, Cairns, cat, clifton views, completion, construction, construction progress, Development, finance, Glencorp, infrastructure, Investment, Investment Property, market, mrd, peak, property, property market, Queensland, rate, report, Research, settlement, strategist, Tenant, water, wednesday, Work